MIDLANDS SERVICE CENTRE BUSINESS PLAN 2003/2004
Date: March 2003
SECTION 1 – INTRODUCTION
The Midlands Service Centre was established in April, 1999 following the reorganisation of CPS into 42 Areas.
The Service Centre provides various administrative services (i.e., Personnel, Finance,
FM, Equality & Diversity and Training) and advice to 745 customers across the
following four CPS Areas:-
- CPS West Midlands
- Birmingham TU/CJU
- Coventry TU/CJU
- Wolverhampton TU
- Black Country CJU’s
- 6 police based Glidewell Units
- Brierley Hill
- Halesowen
- Solihull
- West Bromwich
- Bournville Lane
- Walsall
- CPS Staffordshire
- South Staffordshire Branch
- Newcastle-under-Lyme Branch
- CPS West Mercia
- Hereford & Worcestershire
- Droitwich TU/CJU – based in Droitwich
- Shropshire TU/CJU – based in Shrewsbury
- Hereford & Worcestershire
- CPS Warwickshire
- Warwickshire TU/CJU – Leamington Spa
The Service Centre is managed by Irene Borrill and currently employs 23 staff across 4 teams.
SECTION 2 – OBJECTIVES, PRIORITIES AND DELIVERY OF PSA TARGETS
The three PSA targets are:-
- Narrowing the Justice Gap
- Improving Public Confidence
- Value for Money
2.1 Improving Public Confidence
WITNESSES
Objective - Engage with and provide services to witnesses.
High Risk - Late and inaccurate provision of information from Areas and witnesses.
Countermeasures:
- Put in place SLA with targets (April 2003).
- Monitor compliance with SLA targets, identify poor performance and produce management reports (monthly from April 2003).
- Post payment checking (immediate).
- Training for Service Centre staff (mentoring new staff and ensuring all staff notified of changes).
FINANCE
Objective - Provision of a payment system for Areas.
High Risk - Unreliability of current Ross system.
Countermeasures:
- Business Continuity Plan (April 2003).
- Partnership arrangements with other Service Centres for local Ross problems (immediate)
- Identify urgent/high priority payments for processing in a manual system in case of a system failure (immediate if required).
PAYMENTS
Objective - To process payments (invoices/counsel/agents) within agreed timescales.
High Risks:
- Unreliability of Ross (as previously discussed).
- Late and inaccurate information from Areas.
Countermeasures:
- Awareness training (mentoring new staff and developing ownership)
- Late payment reviews and management reports to Areas from HQ performance figures (monthly-April 2003)
(These countermeasures only have a limited impact on the risks/real issue is that Areas regard payment of invoices as a low priority).
PAY
Objective - Provision of payroll systems to Areas so as to enable the recruitment and retention of competent staff.
High Risks:
- Late and inaccurate information from Areas.
- Lack of experienced Service Centre staff.
- Delay in processing by HQ.
Countermeasures:
- SLA with HQ (April 2003).
- SLA with Areas (April 2003).
- Monitoring and reporting back on poor performance.
- Monitor adherence with SLA targets (after each exercise).
2.2 Value for Money
RECRUITMENT
Objective - Run recruitment exercises in accordance with laid down policies to meet the increased demand for staff.
High Risks:
- Need for speed overrides willingness to conform with laid down policies.
- Lack of Service Centre resources to meet demands.
- Lack of suitable recruits/lowering of standards.
Countermeasures:
- Use of provisional/casual appointments to meet needs (immediate as and when required).
- Realistic/competent sift practices (immediate)
- Switch/review Service Centre resources to recruitment (immediate and constant).
CO-LOCATION
Objective - Provide advice and support on co-location in respect of the CJU/TU and charging initiatives.
High Risks
- Increased demand for assistance in a short timescale when resources are not available to meet this.
- Lack of clarity on what is needed (moving targets/changing demands).
Countermeasures:
- Agree annual co-location plans with Areas (April 2003)/
- Formal change procedures for co-location plans (April 2003).
- Service Centre Managers to set up forum for staff engaged on Facilities Management so as to share knowledge and best practice (June 2004).
PREMISES
Objective - Provide help and advice to enable Areas to meet requirements of DDA and Health and Safety regulations.
High Risks:
- Lack of expertise.
- Areas do not ask for help and advice.
Countermeasures:
- Provide training for staff (as and when required).
- Raise Area awareness (regular monthly bulletins).
- Carry out programme of assessments of premises (biannually – July 2003).
SECTION 3 – SUMMARY OF TARGETS
SECTION 4 – CASELOAD VOLUMES
Not applicable.
SECTION 5 – BUDGET
Please see Annex E.
SECTION 6 – PROFILES OF STAFFING AND NON-RING FENCED ADMINISTRATION SPENDING 2003/2004
See Annex F. in the PDF version of this document: scbpmids.pdf
ANNEX A
KEY RISKS TO ACHIEVEMENT OF PSA TARGETS 2003-2004
AREA/ SERVICE CENTRE:
S04 Midlands
Please show below the five principal risks you have identified to delivery of PSA targets during 2003/04
Risk Number 1: Unreliability of Ross system.
- Owner: Lisa Douglas Head of Finance
- Likelihood/Impact (H,M,L): High/High
- Existing Countermeasures: Business Continuity Plan Partnership with S/Centres Identify urgent priority payments
- Risk Assessment Effectivenss and Sufficiency of countermeasures: This would supply short term cover only. This is for local Ross/server problems only. Prioritise those payments for manual cheques.
- Risk Status (red, amber, green): Amber
- Proposed Countermeasures (with action/review dates): Business Continuity Plan to be done in April 2003. Permanent arrangement to alternative system. Ongoing.
Risk Number 2: Health and Safety - Lack of expertise in the Service Centre and Areas not asking for help.
- Owner: Tony Moore FM Manager
- Likelihood/Impact (H,M,L): Medium/High
- Existing Countermeasures: Provide training for staff. Raise Area awareness. Conduct unannounced H & S checks.
- Risk Assessment Effectivenss and Sufficiency of countermeasures: Effective and up to date. Effective but required frequently and ongoing. Effective if reports acted on by Areas.
- Risk Status (red, amber, green): Amber
- Proposed Countermeasures (with action/review dates): Constant and ongoing. Bulletins to be sent more frequently. Checks to continue bi-annually.
Risk Number 3: Unable to recruit suitable staff quickly.
- Owner: Jim Williams Head of Personnel
- Likelihood/Impact (H,M,L): Medium/High
- Existing Countermeasures: Co-ordinate with other S/Centres and HQ. Realistic/competent sift practice. Switch/review S/C resources.
- Risk Assessment Effectivenss and Sufficiency of countermeasures: Effective and ongoing. Effective however partly dependant on Areas. Effective if timescales are realistic.
- Risk Status (red, amber, green): Amber
- Proposed Countermeasures (with action/review dates): Management info to Areas on board results - ongoing. Recruitment request forms for Areas - ongoing. Timetables produced and adhered to - ongoing.
Risk Number 4: Non-retention of staff.
- Owner: Jim Williams Head of Personnel
- Likelihood/Impact (H,M,L): High/High
- Existing Countermeasures: Close liaison with Areas improved working conditions training and induction.
- Risk Assessment Effectivenss and Sufficiency of countermeasures: Effective however partly dependant on Areas. Effective however dependant on Areas.
- Risk Status (red, amber, green): Amber
- Proposed Countermeasures (with action/review dates): Closer liaison with Areas. Analysis of Exit Reports - as required.
Risk Number 5: Non payment of invoices
- Owner: Lisa Douglas Head of Finance
- Likelihood/Impact (H,M,L): Medium/High
- Existing Countermeasures: Late Payment Report to Areas. Monitoring backlogs. Awareness training for S/C staff.
- Risk Assessment Effectivenss and Sufficiency of countermeasures: Effective only if acted upon by Areas. Effective. Effective.
- Risk Status (red, amber, green): Amber
- Proposed Countermeasures (with action/review dates): Awareness training for the Areas. Continue to review backlogs - ongoing.
ANNEX E
SECTION 5: 2003-04 ADMINISTRATION COSTS BUDGET
AREA NO: 35 AREA NAME: MIDLANDS
Details of Area Allocation Decisions
Total Prosecution Costs: £0
Total Ring Fenced Running Costs £610,000
Total Capital £0